Positioning channels on semi-dry concrete.

In order to achieve a tight connection during installation it is advised to apply a dry set mortar on a female cut out, and after forcing other channel the excessive mortar is to be removed. The next step is to encase the channel side with concrete according to the drawings..

Applying semi-dry concrete under the channels enables to perform levelling precisely and easily.
The class of the concrete used for the strip footings and concrete encasements must not be lower than the class of the substrate and surface to be drained.


The individual parts are connected with one another with frost and water resistant mortars. Expansion joint should be made of bituminous compounds. It is possible to cut the channels – preferably at the place, where the gratings are connected.

 


Mounting and embedding - drainage channels

 

Rysunek techniczny

Szczegółowy opis elementów

Rysunek techniczny

Rysunek techniczny


Odwodnienie z rusztem

Odwodnienie z rusztem

Odwodnienie z rusztem

Pomarańczowa część

POŁĄCZENIE POD KĄTEM

 


Assembly and installation - reinforced concrete drainage with a Type I grate according to the Standard PN-EN 1433:2005

Opisy rysunków technicznych

 

montaz-galeria02
montaz-galeria01
montaz-galeria03

 

Metalowy uchwyt

MOUNTING BRACKETS


Assembly and installation - monolithic slot drainage

Rysunki z opisami

 

 

Odwodnienie monolityczne

Odwodnienie monolityczne 2

Odwodnienie monolityczne 3


Widok wielu elementów

ANGLE CONNECTION